PAVING SCHEDULE FOR AUGUST, 2017

August 20, 2017

Please note the following Paving Schedule for the Town of Freeport:


Main Street in South Freeport Village will get surface pavement August 4 2017 (1 day)

South Freeport Road the second half of the road will get 1 1/2" base pavement August 5 2017 (1 day)

South Freeport Road will get 1 1/2" base pavement August 12 2017 (2 days)

Curtis Road will be reclaimed & reshaped August 14 (3 days)

Curtis Road we will add calcium August 17 2017 (1 day)

Curtis Road will get 3" base pavement (done in two 1 1/2 lifts) August 18 2017 (2 days)

Please expect delays in these areas during paving operations.

FMI: Freeport Public Works 865-4461